Walla Walla City Council approved two budget amendments on September 9, 2026, reallocating $150,000 from the general fund to address emergency sewer line repairs in downtown. The council voted 5-2 in favor of the amendments during a regular meeting.
The funds will be used to repair a 12-inch sewer line on Main Street between 4th and 5th Avenues that experienced a major break on August 28, 2026. The line break caused localized flooding and required temporary water service interruptions for several businesses. City Manager John Smith stated the repairs are necessary to prevent further damage and restore full service.
The council also approved a second amendment to extend the deadline for a public works contract for sidewalk repairs on Oak Street, moving the completion date from October 15 to November 30, 2026.